Here’s the latest progress update of the ongoing New Bukidnon Airport Development Project located in Maray-maray in the Municipality of Don Carlos, Bukidnon as of April 2022. Construction is still under Phase 1 which includes the 1.26-kilometer Runway which is now clearly observed. Check out these latest aerial update courtesy of Project LUPAD.

Also covered under Phase 1 are installation of Concrete Pipe Culverts, Box Culverts and Construction of Apron, North and South Taxiway. Watch below.

Browse photos below.

278709935-544507017033754-3559727699519394738-n
278506082-544507030367086-551379343598869653-n
278614691-544506970367092-7214823471773037120-n
278282423-544506967033759-7033263508898453818-n
278506358-544507000367089-1813196006473152995-n
278739845-544506940367095-7450732807606867046-n
278245573-544507033700419-1830077677021427867-n

Keep posted.