There is now significant progress on the construction of the New Bukidnon Airport located in Maray-maray in the Municipality of Don Carlos with the runway now taking shape. Check out these latest aerial shots courtesy of Trip Outdoor.

First, here’s the map and exact location of the airport project.

LOCD

Phase 1 has an approved budget of P475,416,618.81 and covers concreting of the 1.26-kilometer Runway, Concrete Pipe Culverts, Box Culverts and Construction of Apron, North and South Taxiway.

33454d

Phase 1 is expected to be completed in June 2022.

247433630-426058722571411-7894098752542855882-n

Browse latest aerial photos below. You can clearly see part of the runway.

246494294-426058985904718-2434183018013715572-n
247085586-426058839238066-2788824239990780238-n
247639354-426058942571389-4352436667429910273-n
248502840-426059039238046-6096080179395080489-n
247641922-426058595904757-3347586925767321657-n
247668434-426058802571403-1731191466661434009-n
248030382-426059005904716-1913069789574030929-n
248384291-426058732571410-5450069090464207467-n
246524459-426058769238073-9147007826835607728-n

Phase 1 does not include yet the associated facilities like the control tower and the passenger terminal building.

Watch below.

Keep posted.