101cdo

The Cagayan de Oro Port will be expanded again. At an approved budget cost of P341.77 million, the expansion project will consist of wharf extension, a new platform and additional back-up area of 11,868 sqm.

The Philippine Ports Authority has just published an Invitation to Bid for the said project. See below.

port1

Here’s the location of the expansion.

port

The said project is set for completion in 510 calendar days. View the bidding documents HERE.

Early this year, the PPA also bid out the port’s P284 million 2-storey passenger terminal building with roof deck.

port2

A rendering is shown but image is blurred.

portpas

View bidding documents HERE.

CDO Port photo from www.ppa.gov.ph