PROJECT WATCH: Aspira Tower 1 pile capping works continue

In its official project update (as of February 2016), pile hacking and pile capping works are still ongoing for Tower 1 of Avida Towers Aspira.

As shown below (taken from Avida Land website), percentage completion was placed at 22.73%. You can also notice some vertical works now also underway. Construction work has sped up for the project located along Ramon Chaves Street in Cagayan de Oro City.


Meanwhile, the project’s t-crane is now very visible in the city’s downtown area.


Visit the website HERE.