Here are latest photo updates of the ongoing Bitan-ag Bridge Project located along CM Recto Avenue in downtown Cagayan de Oro City.

As shown, traffic has been moderate and controlled so far since construction began.IMG_8020

Heavy equipment are seen onsite.

IMG_8021 IMG_8022

Piling works are observed at the bridge site.

IMG_8023

Section of CM Recto Avenue fronting MUST has been excavated.IMG_8025

Excavation works are necessary prior to earthfilling.

IMG_8026

Highway culverts are also seen onsite.IMG_8027

Portions of CM Recto are already filled up with earth materials up to the island level.IMG_8028 IMG_8029 IMG_8031

This road is expected to rise at the bridge point along the creek.IMG_8032 IMG_8033 IMG_8034 IMG_8036 IMG_8037 IMG_8038

 

Despite the delays, hopefully this project will serve its purpose as planned.