The Department of Public Works and Highways (DPWH) is set to construct a bridge over Bitan-ag Creek in Cagayan de Oro City to address the perennial overflowing of said creek.

A billboard posted near the site as shown below states that the project costs some P63.59 million including approaches.20689_10203162933949188_5633582931967807030_n

The project contractor is Jejor’s Construction Corp. and scheduled to be completed in 230 calendar days or around October 24, 2015.11076285_10203162933709182_5727990701783321631_n

Bitan-ag Creek currently flows under CM Recto Avenue through a pair of culverts which have become inadequate as experienced in the past few years. The overflowing of said creek have affected Limketkai Center, Mindanao University of Science & technology (MUST) and surrounding areas. The project also aims to improve the drainage system in the area.