The JR Borja Bridge’s approach at Carmen has been completed.

As shown, concreting works including side barriers and sidewalks have been accomplished already.

IMG_8754

The whole span of the Spanish-funded bridge across Cagayan de Oro River has been completed a few weeks ago but the eastern approach at Burgos Street still has that one huge house blocking the right-of-way which has not been demolished yet.

IMG_8755 IMG_8756

You could see the house at the end of the bridge…

IMG_8757 IMG_8758

Below is the intersection along Vamenta Boulevard in Carmen. A traffic light has been installed already but not yet operating.IMG_8759 IMG_8760 IMG_8761

Se decorative ties marked the new sidewalk.

IMG_8762 IMG_8763 IMG_8764

The new bridge has a carrying capacity of up to 20 tons.

IMG_8765

 

DPWH has set the target of completion for this bridge in January 2015.