Construction of Mindanao University of Science & Technology (MUST) Engineering Complex is now progressing to the 3rd and 4th levels.

As shown in the photos taken yesterday, the three lower floors are already undergoing concreting while the columns are rising towards the 4th floor. To note, this complex is composed of two buildings. The building at right will have five floors while the taller building on the left will rise eight (8) storeys. You could notice the building’s ground floor now elevated from the highway by at least 5 feet or approximately 1.5 meters as a measure against flooding.

IMG_8576 IMG_8577 IMG_8578 IMG_8579