Work on the Recto-Velez flyover has now shifted on the flyover pavement as well as both approaches.

As shown in the following pictures taken on two occasions today, one in early morning and the other at noon, contractor UKC Builders has installed nets under the main girders to catch anything which may fall from construction work above. Filling materials also have been dumped on both approaches. Today is September 16 and at the rate, I can see completion in October and could be passable by vehicles before November.