Latest updates of the Laguindingan Airport Development Project shows continuing work on the Control Tower (above) and other buildings and facilities in the airport complex.

Rains brought by Typhoon Urduja somewhat caused some minor delays but still as a whole, LADP is still ahead of schedule based on information gathered.

More photos of the Control Tower are seen below. 

Work on the Passenger Terminal Building is now on the second floor.

Workers from various contractors are rushing their work on all other facilities in the complex.

Below is the status of the Power House Building.

More photos of the Passenger Terminal Building.

Paving of the road network around the complex continues. The project has resulted to a significant rise in income by Holcim which supplies the cement requirement of the project. In fact, the company is said to be expanding to meet the demand next year. 

This is the view of the airport complex from the 4-kilometer access road.