Powerpoint screenshots on LADP Project updates. Civil works are 50.6686% complete as of September 27, 2009 or 11.0880 % or 2.60 calendar months ahead of schedule.

3989187396_826ed654cf

3988432135_b23e844848

The 4-lane 4.392 kilometer access road from airport to the national highway is 98.82% substantually completed.