Building “B” of the Mallberry Suites Triple Building Expansion Project is now fast rising beside the current building which is technically referred to as Building “A”. As of this post, installation of the steel structural frames is now on the 6th floor of “B” and going to the 7th floor.

As seen below, structural steel frames of Building “C” which is 10 storeys high, and of Building “D” which has 7 storeys, are already complete. Building “D” looked like 8 storeys but the supposed 8th storey is really meant for utilities such as water tanks for the hotel’s consumption.

100_5588b

100_5589

100_5590

Based on the construction progress, the expansion would be completed before the year ends or by 1st quarter of next year. All photos were taken from the southwest point of view of the hotel.